Critical path: The critical path is the sequence of activities that must be completed on schedule for the entire project to be completed on schedule. It is the longest duration path through the workplan. If an activity on the critical path is delayed by one day, the entire project will be delayed by one day (unless another activity on the critical path can be accelerated by one day). [1]
This video gives a simplified version to explain the concept.
ARVE Error: maxwidth:
560px
is not valid
Video
Critical path: The critical path is the sequence of activities that must be completed on schedule for the entire project to be completed on schedule. It is the longest duration path through the workplan. If an activity on the critical path is delayed by one day, the entire project will be delayed by one day (unless another activity on the critical path can be accelerated by one day). [1]
This video gives a simplified version to explain the concept.
560px
is not validReading
You must be logged in to post to WEnotes.
Note: Your comment will be displayed in the course feed.